0.20 Release
Status
- 21 January: 0.20 is GA
- 10 January: Proposed final RC4 is available at revision 1430909 of the 0.20 release branch
- 18 December: RC3 is available at revision 1423691 of the 0.20 release branch
- 7 December: RC2 is available at revision 1418220 of the 0.20 release branch
- 3 December: RC1 is available at revision 1415325 of the 0.20 release branch
- 19 November: Beta is cut at revision 1411386 of the 0.20 release branch
- 19 November: Release branch created at revision 1411210 of trunk
- 1 November: Alpha 2 is cut at revision 1404590 of trunk
- 1 November: Beta is postponed to 14 November
- 25 October: Alpha is cut at revision 1402191 of trunk
- 9 July: Trunk is open for 0.20 development at revision 1359193
Issues
Features and improvements |
http://bit.ly/VgrQSY |
Open bugs |
http://bit.ly/UkvM6r |
Fixed bugs |
http://bit.ly/SGNAJ3 |
Candidate bugs |
http://bit.ly/THBD4t |
Distributions
Links
Release branch |
https://svn.apache.org/repos/asf/qpid/branches/0.20/ |
Release tag |
https://svn.apache.org/repos/asf/qpid/tags/0.20/ |
Schedule
17 October
- Alpha
- Major feature integration ends; with approval, certain less disruptive features can be committed
- Trunk remains open for bug fixing
- The alpha release tests the release process after the introduction of major features
31 October, 2 weeks later
- Alpha 2
31 October 14 November, 2 weeks later
- Beta
- The release branch is created
- Trunk opens for development toward the next release
- Release branch commits require approval
- Release manager produces outstanding bug report and triages bugs
14 November 28 November, 2 weeks later
- RC1
21 November 5 December, 1 week later
- RC2
28 November 12 December, 1 week later
- RC3
- Targeted release date