Timing

Dec 17 - Jan 18Jan 18Feb 1Feb 15

PlannedActual
Planning PhaseDec 17 - Jan 7Nov 13 - Nov 27
Announce ReleaseJan 7Nov 27
QAJan 7 - Jan 21Jan 28 - Feb 1Nov 27 - Dec 11
Publish Release NotesJan 21Dec 11 
Vote on ReleaseJan 28Feb 8Dec 18
Target Release DateFeb 5Dec 25

Scope

There are main goals of this release

...

  • Changes contributed by Partners including:
    • Enhancements led by Mifos, developed by DPC with support from DIAL around Open Banking
    • GSOC Hardening
    • Partner Contributions
    • GSIM/GLIM