Start Date | Description |
---|
2020-02-18 | Preparation - schedule, pages, Synergy (3 days) |
2020-02-21 | NetCAT 12.0 invitation sent, volunteers start joining |
2020-03-02 | Review of test specifications (2 weeks) |
2020-03-13 | Synergy test run prepared |
2020-03-16 | Official 6-weeks certification starts on vc1 |
2020-03-30 | Request to switch to vc2 sent |
2020-04-03 | 1/2 way sync-up with tribe leaders |
20192020-0304-0713 | Request to switch to vc3 sent |
20192020-0304-1127 | Community Acceptance 2-weeks survey launched for vc3 |
20192020-0305-1804 | Certification completed, blockers fixed in vc4 or waived |
20192020-0305-2208 | Community Acceptance survey closed and results published, satisfaction survey launched |
2020-05-08 | Sanity check of Apache NetBeans 12.0 GA build (4 days) |
2020-05-12 | Apache NetBeans 12.0 GA voting thread started (3 days) |
2020-05-15 | Apache NetBeans 12 | 2019-03-28 | Apache NetBeans 11.0 released |
20192020-0305-2915Satisfaction survey closed and results published, NetCAT 11 | NetCAT 12.0 Satisfaction survey (1 week) |
2020-05-22 | NetCAT 12.0 closed |